Honley High School Remodel

The work included this Design and Build project to remodel Block C and provide an improved facility for the SEN Department at this council funded secondary school.

The reconfiguration of several classrooms created a learning space for Key Stage 3 and 4, a common room, staff monitoring area, new kitchen, and new toilets.

A number of additional one to one rooms and two sensory rooms where also constructed. A new entrance was also created comprising of an aluminium door screen with a ramped access and handrails.

The work included the reconfiguration of several classrooms creating a learning space for Key Stage 3 and 4, a common room, staff monitoring area, new kitchen, and new toilets.  A number of additional one to one rooms and two sensory rooms where also constructed. A new entrance was created comprising of an aluminium door screen with a ramped access and handrails.

Works included

  • Stripping out
  • IPS Cabinets and cubicles
  • Structural alterations
  • M&E reconfiguration works
  • Timber door sets joinery works
  • Internal and external windows and doors
  • Flooring
  • External ramp and handrails
  • Lighting and DATA points
  • Stud Walling, plastering, decoration and suspended ceilings
  • Duration / weeks8
  • Project value£295k
  • LocationHonley, Huddersfield
  • CustomerKirklees School Services